If a downtime of around 15min on such migration task is too long for your environment you probably need to adjust redundancy on software level. So having 2 Domain Controllers results in no downtime even if one is turned off. Same for SQL-Cluster, Fileserver-Cluster,… Design it that way and you keep up production workloads even if one vm is turned off due to migration, patch-installation, …
Haven’t seen VM-Level replication between HyperV and VMware so far. You might create VMware Host on HyperV in Nested virtualisation, to move workload to another host and then maybe reduce downtime further - but probably not worth the effort!
Haven’t seen VM-Level replication between HyperV and VMware so far. You might create VMware Host on HyperV in Nested virtualisation, to move workload to another host and then maybe reduce downtime further - but probably not worth the effort!
Statistics: Posted by f.neumann — Mar 11, 2024 9:55 am